Energy Projects Near You

Solar, wind and battery projects near Great Yarmouth (NR29)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NR29 (Great Yarmouth): 5 approved but not yet running, 3 operational. The largest live scheme is Seashore Holiday Park, North Drive (0.5 MW rooftop solar, approved on 7 June 2023, not yet built; REPD status may be out of date), 2.5 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Scroby Sands (60 MW, operational), 11.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
0awaiting a decision
5approved, not running
3operational

Projects within 10 km of NR29

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
South Beach Wind Turbine (Somerton)wind turbinewind turbine1.5operationalupdated May 2013May 1999granted Apr 2000May 2013Great Yarmouth2.1
Blood Hill Wind Farmwind farmwind farm2.3decommissionedupdated Jan 2015Mar 1998refused Aug 1999Jan 2015Great Yarmouth2.1
Bloodhills - repoweringwind farmwind farm1operationalupdated Nov 2015Feb 2013granted May 2013Nov 2015Great Yarmouth2.3
Hemsby Wind Farmwind farmwind farm10refusedupdated Jan 2011Sep 2009refused Dec 2009Jan 2011Great Yarmouth3.0
Nova Scotia Farm solar parksolar farmsolar farm13.9operationalupdated Jan 2017Apr 2013granted Jul 2013Jan 2017Great Yarmouth5.6
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Seashore Holiday Park, North Driverooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jul 2023Apr 2023granted Jun 2023Jul 2023Great Yarmouth2.5
ABB & UK Power Networks Energy Storage Installationbattery storagebattery storage0.2decommissionedupdated Oct 2018——Oct 2018Great Yarmouth3.2
Herbert Woods, Bridge Roadrooftop solarrooftop solar0.2application withdrawnupdated Apr 2023Jan 2023—Apr 2023Great Yarmouth3.5
Caister Holiday Centre, Ormesby Roadrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Jul 2023Apr 2023granted Jun 2023Jul 2023Great Yarmouth7.0
Laurels Farm, Laurels Roadsolar farmsolar farm0.2approved, not built may be out of dateupdated Mar 2023Oct 2022granted Feb 2023Mar 2023North Norfolk7.1
The Pump House - Ground Mounted Solar Photovoltaic Arraysolar farmsolar farm0.3approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Broadland9.6
Seashore Holiday Park, North Driverooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023Apr 2023granted Jun 2023Jul 2023Great Yarmouth9.8

Distance from the average position of the NR29 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm302100.5
Rooftop solar403001.2
Wind farm300110
Wind turbine100100
Battery storage100000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Scroby Sands60operationalupdated Feb 201611.7
East Anglia 2 (EA 2)900approved, not builtupdated Apr 202235.9

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Great Yarmouth decides solar, wind and battery applications

ApplicationsGreat YarmouthUK
Decided applications (solar, wind, battery)1610,236
Refused2 (12%)19%
Solar refused0 of 912%
Onshore wind refused2 of 545%
Battery storage refused0 of 216%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Great Yarmouth

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NR29, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.