Energy Projects Near You

Solar, wind and battery projects near Norwich (NR13)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NR13 (Broadland): 3 are waiting for a planning decision, 6 approved but not yet running, 2 operational. The largest live scheme is Avenue Farm - Back Road Solar Farm (15 MW solar farm, application submitted on 29 May 2025, no decision recorded), 9.0 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Scroby Sands (60 MW, operational), 22.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
3awaiting a decision
6approved, not running
2operational

Projects within 10 km of NR13

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Salhouse Solar Farmsolar farmsolar farm5operationalupdated Dec 2015Oct 2013granted Feb 2014Dec 2015Broadland7.3
Avenue Farmsolar farmsolar farm7.3operationalupdated May 2015Mar 2014granted Oct 2014May 2015South Norfolk8.3
Avenue Farm - Back Road Solar Farmsolar farmsolar farm15application submittedupdated Jul 2025May 2025—Jul 2025South Norfolk9.0
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Yarmouth Road, Blofield Solar Park, Battery Storage, Cafes & Retailsolar farmsolar farm—application submittedupdated May 2026Feb 2026—May 2026Broadland2.3
Yarmouth Road, Blofield Solar Park, Battery Storage, Cafes & Retailbattery storagebattery storage—application submittedupdated May 2026Feb 2026—May 2026Broadland2.3
The Pump House - Ground Mounted Solar Photovoltaic Arraysolar farmsolar farm0.3approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Broadland4.3
D And F Mccarthy Limited, Memorial Wayrooftop solarrooftop solar0.3approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Broadland6.0
Burtt Way, Great Plumstead Solar Battery Storagebattery storagebattery storage0.3approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Broadland6.0
John Menzies Distribution, Memorial Wayrooftop solarrooftop solar0.2approved, not builtupdated Feb 2023Dec 2022granted Jan 2023Feb 2023Broadland6.1
Wendover Road, Rackheathrooftop solarrooftop solar0.3approved, not builtupdated Dec 2021Oct 2021granted Dec 2021Dec 2021Broadland7.5
Tesco Storesrooftop solarrooftop solar0.3approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Broadland9.0

Distance from the average position of the NR13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5212015.3
Rooftop solar404001.1
Battery storage211000.3

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Scroby Sands60operationalupdated Feb 201622.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Broadland decides solar, wind and battery applications

ApplicationsBroadlandUK
Decided applications (solar, wind, battery)2210,236
Refused7 (32%)19%
Solar refused4 of 1712%
Onshore wind refused2 of 245%
Battery storage refused1 of 316%
Median time from submission to decision18.3 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Broadland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.