Avenue Farm - Back Road Solar Farm (15 MW)

Avenue Farm - Back Road Solar Farm is a 15 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 29 May 2025, no decision recorded; the record was last updated on 22 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
application submittedstatus in REPD
22 July 2025record last updated
South Norfolkcouncil area

Planning timeline

DateStage
29 May 2025Application submitted

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
application submitted
Record last updated
22 July 2025
Operator or applicant
South Norfolk & Broadland
Planning authority
South Norfolk
Planning application reference
2025/1442
Site area
29.4 ha
Address (REPD)
Avenue Farm, Back Road, Yelverton, Norwich
Council area (by location)
South Norfolk
REPD reference
19124

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Avenue Farmsolar farm7.3operational0.7
Land East of White Horse Lanesolar farm5operational6.7
White Horse Lane (Trowse) - Phase 2solar farm9approved, not built6.7
Stoke Lanebattery storage130approved, not built7.3
Norwich Substation Storage Facilitybattery storage49.9approved, not built7.4
Hickling Lane, Swainsthorpe -Battery Storagebattery storage114approved, not built7.4
Hempnallwind farm21refused on appeal8.0
Mulbarton Road, Keswickbattery storage400application submitted8.1
Bloy’s Grove Solar Farmsolar farm49.9approved, not built8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5696, 1.3856).