Hempnall (21 MW wind farm)

Hempnall is a 21 MW wind farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 8 December 2009; the record was last updated on 6 December 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
refused on appealstatus in REPD
6 December 2010record last updated
South Norfolkcouncil area

Planning timeline

DateStage
1 June 2008Application submitted
5 August 2008Refused by the planning authority
8 December 2009Appeal refused

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
refused on appeal
Record last updated
6 December 2010
Operator or applicant
Enertrag UK
Planning authority
South Norfolk
Planning application reference
07/2008/0917/F
Turbines
7
Address (REPD)
Land at Busseys Loke, Hempnall Norfolk
Council area (by location)
South Norfolk
Time to decision
9 weeks
REPD reference
3519

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Streetwood Wind Farmwind farm12refused0.6
Hall Farm Solar parksolar farm15operational1.6
Bloy’s Grove Solar Farmsolar farm49.9approved, not built6.2
East Pye Solar Farmsolar farm500application submitted6.7
Land south of Brick Kiln Roadsolar farm5operational7.0
Stoke Lanebattery storage130approved, not built7.1
Norwich Substation Storage Facilitybattery storage49.9approved, not built7.9
Hickling Lane, Swainsthorpe -Battery Storagebattery storage114approved, not built7.9
Avenue Farm - Back Road Solar Farmsolar farm15application submitted8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5086, 1.324).