Hall Farm Solar park (15 MW)

Hall Farm Solar park is a 15 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2016; the record was last updated on 4 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
operationalstatus in REPD
4 March 2016record last updated
South Norfolkcouncil area

Planning timeline

DateStage
21 March 2014Application submitted
24 October 2014Planning permission granted
15 February 2016Operational

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
4 March 2016
Operator or applicant
Solar Park Developments (Blackrock)
Planning authority
South Norfolk
Planning application reference
2014/0562
Address (REPD)
Land South Of Hall Farm Bungay Road Tasburgh Norfolk
Council area (by location)
South Norfolk
Time to decision
31 weeks
REPD reference
1108

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Streetwood Wind Farmwind farm12refused1.1
Hempnallwind farm21refused on appeal1.6
East Pye Solar Farmsolar farm500application submitted5.2
Bloy’s Grove Solar Farmsolar farm49.9approved, not built6.7
Hill Farm, Wacton Roadbattery storage120approved, not built7.2
Land south of Brick Kiln Roadsolar farm5operational7.3
Wymondham Road, Bracon Ashbattery storage228application submitted7.9
Stoke Lanebattery storage130approved, not built7.9
Flordon Road, Bracon Ash Solar Panels & Battery Storagesolar farm24approved, not built7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4976, 1.3092).