Energy Projects Near You

Solar, wind and battery projects near Bungay (NR35)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NR35 (South Norfolk): 1 is waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Redisham Hall Farm, School Road (42 MW solar farm, application submitted on 10 June 2025, no decision recorded), 7.4 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Scroby Sands (60 MW, operational), 31.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
1awaiting a decision
1approved, not running
1operational

Projects within 10 km of NR35

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Laurels Farmwind turbinewind turbine2permission expiredupdated May 2020Nov 2012granted Apr 2014May 2020East Suffolk5.2
Stockton Wind Turbinewind farmwind farm1.5refusedupdated Aug 2005Mar 1998refused May 2001Aug 2005South Norfolk6.4
Redisham Hall Farm, School Roadsolar farmsolar farm42application submittedupdated Aug 2025Jun 2025—Aug 2025East Suffolk7.4
Granary farmwind farmwind farm9refusedupdated Sep 2011Jul 2010refused Oct 2010Sep 2011East Suffolk7.5
Brundish Wind Turbinewind farmwind farm1.5refusedupdated May 2006Mar 1998refused May 2001May 2006South Norfolk7.7
Devonshire Farmwind farmwind farm9refusedupdated Sep 2011Jul 2010refused Oct 2010Sep 2011East Suffolk8.1
Hempnallwind farmwind farm21refused on appealupdated Dec 2010Jun 2008refused Aug 2008Dec 2010South Norfolk9.0
Hall Farm Solar parksolar farmsolar farm15operationalupdated Mar 2016Mar 2014granted Oct 2014Mar 2016South Norfolk9.3
Streetwood Wind Farmwind farmwind farm12refusedupdated Sep 2014Jan 2013refused Oct 2014Sep 2014South Norfolk9.5
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Morrisons, George Westwood Way - Photovoltaic Arrayrooftop solarrooftop solar—approved, not builtupdated Dec 2021Nov 2021granted Jan 2022Dec 2021East Suffolk9.4

Distance from the average position of the NR35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2101042
Rooftop solar101000
Wind farm600060
Wind turbine100000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Scroby Sands60operationalupdated Feb 201631.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How South Norfolk decides solar, wind and battery applications

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in South Norfolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.