Energy Projects Near You

Solar, wind and battery projects near Harleston (IP20)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP20 (South Norfolk): 4 are waiting for a planning decision, 3 approved but not yet running. The largest live scheme is East Pye Solar Farm (500 MW solar farm, application submitted on 2 April 2026, no decision recorded), 9.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
4awaiting a decision
3approved, not running
0operational

Projects within 10 km of IP20

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pulham Airfieldwind farmwind farm14application withdrawnupdated Sep 2008——Sep 2008South Norfolk6.5
Upper Vaunces Wind Farmwind farmwind farm6refusedupdated Mar 2015Apr 2013refused Aug 2013Mar 2015South Norfolk7.0
Semere Lane, Dickleburgh Solar Farmsolar farmsolar farm49.9application submittedupdated Aug 2025Jul 2025—Aug 2025South Norfolk8.3
East Pye Solar Farmsolar farmsolar farm500application submittedupdated May 2026Apr 2026—May 2026South Norfolk9.1
Tivetshall St Mary Wind Farmwind farmwind farm9application withdrawnupdated May 2013Mar 2010—May 2013South Norfolk9.3
Station Road, Tivetshall St Margaretsolar farmsolar farm20approved, not builtupdated Feb 2026Dec 2024granted Jun 2025Feb 2026South Norfolk9.4
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
East Of England Co Op, Bullock Fair Closerooftop solarrooftop solar0.2application submittedMay 2026——South Norfolk1.4
East Pye Solar Farmbattery storagebattery storage—application submittedupdated May 2026Apr 2026—May 2026South Norfolk9.1
Peddars Milling, Mill Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025South Norfolk9.7
Roger Skinnerrooftop solarrooftop solar0.6approved, not builtupdated Sep 2021Aug 2021granted Sep 2021Sep 2021Mid Suffolk10.0

Distance from the average position of the IP20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm32100570
Rooftop solar312001.2
Wind farm300010
Battery storage110000

MW in pipeline: pending, approved and under-construction capacity.

How South Norfolk decides solar, wind and battery applications

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in South Norfolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.