Energy Projects Near You

Upper Vaunces Wind Farm (6 MW)

Upper Vaunces Wind Farm is a 6 MW wind farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 21 August 2013; the record was last updated on 9 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
refusedstatus in REPD
9 March 2015record last updated
South Norfolkcouncil area

Planning timeline

DateStage
26 April 2013Application submitted
21 August 2013Refused by the planning authority
16 September 2013Appeal lodged
15 January 2015Appeal refused
15 January 2015Secretary of State refused

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
refused
Record last updated
9 March 2015
Operator or applicant
Upper Vaunces Wind Farm
Planning authority
South Norfolk
Planning application reference
2013/0725
Appeal reference
APP/L2630/A/13/2203839
Turbines
3
Address (REPD)
Land east of Semere Green Road (forming part of Upper Vaunces Farm)
Council area (by location)
South Norfolk
Time to decision
17 weeks
REPD reference
4470

Earlier applications for this site

ApplicationMWSubmittedOutcome
Upper Vaunces Wind Farm 2010/03837.59 March 2010refused 20 December 2010

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pulham Airfieldwind farm14application withdrawn0.5
Semere Lane, Dickleburgh Solar Farmsolar farm49.9application submitted1.3
Tivetshall St Mary Wind Farmwind farm9application withdrawn2.9
Station Road, Tivetshall St Margaretsolar farm20approved, not built3.5
Solar Farm at Marsh Lane Solar Farm At Land North Of Lion Road Palgravesolar farm30approved, not built7.1
Market Lane And Carr Lane, Great Moultonbattery storage400application submitted7.4
East Pye Solar Farmsolar farm500application submitted7.5
Hill Farm, Wacton Roadbattery storage120approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4084, 1.2163).