Solar Farm at Marsh Lane Solar Farm At Land North Of Lion Road Palgrave (30 MW)

Solar Farm at Marsh Lane Solar Farm At Land North Of Lion Road Palgrave is a 30 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 August 2025, not yet built; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
19 February 2026record last updated
South Norfolkcouncil area

Planning timeline

DateStage
4 December 2023Application submitted
13 August 2025Planning permission granted
13 August 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
19 February 2026
Operator or applicant
Aura Power Storage Solutions
Planning authority
South Norfolk
Planning application reference
DC/23/05426
Site area
57.6 ha
Address (REPD)
Marsh Lane Solar Farm At Land North Of Lion Road Palgrave, Diss
Council area (by location)
South Norfolk
Time to decision
88 weeks
Contracts for Difference
AR7a
Name in REPD
Marsh Lane Solar Farm, Lion Road - Solar Farm
REPD reference
13987

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Grange Solar Farm & Battery Storagesolar farm48approved, not built3.2
Humphrey Groupwind farm5operational4.2
Yaxley, Eye Airfield Industrial Estatebattery storage200approved, not built4.2
J.W. Baldwin Wind Farmwind farm6.8application withdrawn4.9
Red House Farm, Old Norwich Roadbattery storage520application submitted5.4
Semere Lane, Dickleburgh Solar Farmsolar farm49.9application submitted5.9
Tivetshall St Mary Wind Farmwind farm9application withdrawn6.9
Upper Vaunces Wind Farmwind farm6refused7.1
Pulham Airfieldwind farm14application withdrawn7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3741, 1.1279).