The Grange Solar Farm & Battery Storage (48 MW)

The Grange Solar Farm & Battery Storage is a 48 MW solar farm project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 November 2023, not yet built; the record was last updated on 31 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWsolar farm
approved, not builtstatus in REPD
31 March 2026record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
14 June 2022Application submitted
9 November 2023Planning permission granted
9 November 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
48 MW
Status (REPD)
approved, not built
Record last updated
31 March 2026
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
Mid Suffolk
Planning application reference
DC/22/02667
Site area
90.0 ha
Address (REPD)
Grange Farm, Old Bury Road, Palgrave, Diss
Council area (by location)
Mid Suffolk
Time to decision
73 weeks
Contracts for Difference
AR7a
REPD reference
20389

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Humphrey Groupwind farm5operational2.9
Yaxley, Eye Airfield Industrial Estatebattery storage200approved, not built2.9
Solar Farm at Marsh Lane Solar Farm At Land North Of Lion Road Palgravesolar farm30approved, not built3.2
Red House Farm, Old Norwich Roadbattery storage520application submitted3.3
J.W. Baldwin Wind Farmwind farm6.8application withdrawn3.4
Suggenhall Farm - Photovoltaic Solar Array & Battery Storagesolar farm7.3approved, not built6.7
Semere Lane, Dickleburgh Solar Farmsolar farm49.9application submitted9.0
Whitebreads Farmsolar farm10refused9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3539, 1.0946).