Energy Projects Near You

Suggenhall Farm - Photovoltaic Solar Array & Battery Storage (7.3 MW)

Suggenhall Farm - Photovoltaic Solar Array & Battery Storage is a 7.3 MW solar farm project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 April 2024, not yet built; the record was last updated on 26 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.3 MWsolar farm
approved, not builtstatus in REPD
26 April 2024record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
18 December 2021Application submitted
3 August 2022Refused by the planning authority
4 January 2023Appeal lodged
17 April 2024Planning permission granted
17 April 2024Appeal allowed
17 April 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
7.3 MW
Status (REPD)
approved, not built
Record last updated
26 April 2024
Operator or applicant
RNA Energy Limited
Planning authority
Mid Suffolk
Planning application reference
DC/21/06825
Appeal reference
AP/23/00002
Site area
12.3 ha
Address (REPD)
The S/O Suggenhall Farm Church Lane Rickinghall
Council area (by location)
Mid Suffolk
Time to decision
122 weeks
REPD reference
10164

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Potash Farmwind farm6.6refused6.4
The Grange Solar Farm & Battery Storagesolar farm48approved, not built6.7
Whitebreads Farmsolar farm10refused7.0
Red House Farm, Old Norwich Roadbattery storage520application submitted7.5
J.W. Baldwin Wind Farmwind farm6.8application withdrawn8.4
Humphrey Groupwind farm5operational8.4
Yaxley, Eye Airfield Industrial Estatebattery storage200approved, not built8.4
Solar Farm at Marsh Lane Solar Farm At Land North Of Lion Road Palgravesolar farm30approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3301, 1.0034).