Yaxley, Eye Airfield Industrial Estate (200 MW battery storage)

Yaxley, Eye Airfield Industrial Estate is a 200 MW battery storage project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 July 2025, not yet built; the record was last updated on 28 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
28 July 2025record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
20 December 2024Application submitted
4 July 2025Planning permission granted
4 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
28 July 2025
Operator or applicant
Field Yaxley Limited
Planning authority
Mid Suffolk
Planning application reference
DC/24/05535
Address (REPD)
S/o Eye Airfield Industrial Estate Castleton Way Yaxley, Eye
Council area (by location)
Mid Suffolk
Time to decision
28 weeks
Name in REPD
Yaxley, Eye Airfield Industrial Estate - Battery Storage System
REPD reference
17833

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Humphrey Groupwind farm5operational<0.1
J.W. Baldwin Wind Farmwind farm6.8application withdrawn0.7
Red House Farm, Old Norwich Roadbattery storage520application submitted1.4
The Grange Solar Farm & Battery Storagesolar farm48approved, not built2.9
Solar Farm at Marsh Lane Solar Farm At Land North Of Lion Road Palgravesolar farm30approved, not built4.2
Suggenhall Farm - Photovoltaic Solar Array & Battery Storagesolar farm7.3approved, not built8.4
Semere Lane, Dickleburgh Solar Farmsolar farm49.9application submitted9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3366, 1.1268).