Energy Projects Near You

Humphrey Group (5 MW wind farm)

Humphrey Group is a 5 MW wind farm project in Mid Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 February 2013; the record was last updated on 4 March 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
operationalstatus in REPD
4 March 2013record last updated
Mid Suffolkcouncil area

Planning timeline

DateStage
12 March 2010Application submitted
20 July 2010Planning permission granted
9 January 2013Construction started
25 February 2013Operational

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 March 2013
Operator or applicant
Roy Humphrey Group
Planning authority
Mid Suffolk
Planning application reference
0724/10
Turbines
2
Address (REPD)
Eye Airfield Industrial Estate, Ipswich Road, Brome, Eye, Suffolk, IP23 8AW
Council area (by location)
Mid Suffolk
Time to decision
19 weeks
REPD reference
3672

Who decides

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Yaxley, Eye Airfield Industrial Estatebattery storage200approved, not built<0.1
J.W. Baldwin Wind Farmwind farm6.8application withdrawn0.7
Red House Farm, Old Norwich Roadbattery storage520application submitted1.4
The Grange Solar Farm & Battery Storagesolar farm48approved, not built2.9
Solar Farm at Marsh Lane Solar Farm At Land North Of Lion Road Palgravesolar farm30approved, not built4.2
Suggenhall Farm - Photovoltaic Solar Array & Battery Storagesolar farm7.3approved, not built8.4
Semere Lane, Dickleburgh Solar Farmsolar farm49.9application submitted9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3367, 1.1266).