Tivetshall St Mary Wind Farm (9 MW)
Tivetshall St Mary Wind Farm is a 9 MW wind farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 4 March 2013; the record was last updated on 8 May 2013.
9 MWwind farm
application withdrawnstatus in REPD
8 May 2013record last updated
South Norfolkcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 2 March 2010 | Application submitted |
| 4 March 2013 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 9 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 8 May 2013
- Operator or applicant
- Enertrag UK
- Planning authority
- South Norfolk
- Planning application reference
- 2010/0861
- Turbines
- 3
- Address (REPD)
- Wind Farm at Land to the west of New Road, Tivetshall St Mary, Norfolk
- Council area (by location)
- South Norfolk
- REPD reference
- 3977
Who decides
| Applications | South Norfolk | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 50 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 1 of 30 | 12% |
| Onshore wind refused | 7 of 7 | 45% |
| Battery storage refused | 0 of 13 | 16% |
| Median time from submission to decision | 20.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Station Road, Tivetshall St Margaret | solar farm | 20 | approved, not built | 1.0 |
| Semere Lane, Dickleburgh Solar Farm | solar farm | 49.9 | application submitted | 2.3 |
| Upper Vaunces Wind Farm | wind farm | 6 | refused | 2.9 |
| Pulham Airfield | wind farm | 14 | application withdrawn | 3.2 |
| Market Lane And Carr Lane, Great Moulton | battery storage | 400 | application submitted | 5.2 |
| East Pye Solar Farm | solar farm | 500 | application submitted | 6.6 |
| Solar Farm at Marsh Lane Solar Farm At Land North Of Lion Road Palgrave | solar farm | 30 | approved, not built | 6.9 |
| Hill Farm, Wacton Road | battery storage | 120 | approved, not built | 7.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4256, 1.185).