Avenue Farm (7.3 MW solar farm)

Avenue Farm is a 7.3 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 March 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.3 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
South Norfolkcouncil area

Planning timeline

DateStage
4 March 2014Application submitted
31 October 2014Planning permission granted
3 December 2014Construction started
20 March 2015Operational

Project details

Technology
solar farm
Capacity
7.3 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
South Norfolk
Planning application reference
2014/0411
Site area
16.8 ha
Address (REPD)
Land North Of Avenue Farm Back Road Yelverton Norfolk
Council area (by location)
South Norfolk
Time to decision
34 weeks
REPD reference
1909

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Avenue Farm - Back Road Solar Farmsolar farm15application submitted0.7
White Horse Lane (Trowse) - Phase 2solar farm9approved, not built6.5
Land East of White Horse Lanesolar farm5operational6.5
Stoke Lanebattery storage130approved, not built7.6
Norwich Substation Storage Facilitybattery storage49.9approved, not built7.7
Hickling Lane, Swainsthorpe -Battery Storagebattery storage114approved, not built7.7
Mulbarton Road, Keswickbattery storage400application submitted8.1
Bloy’s Grove Solar Farmsolar farm49.9approved, not built8.7
Hempnallwind farm21refused on appeal8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5757, 1.389).