Energy Projects Near You

Salhouse Solar Farm (5 MW)

Salhouse Solar Farm is a 5 MW solar farm project in Broadland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 October 2015; the record was last updated on 16 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 December 2015record last updated
Broadlandcouncil area

Planning timeline

DateStage
8 October 2013Application submitted
5 February 2014Planning permission granted
29 July 2015Construction started
20 October 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 December 2015
Operator or applicant
Island Green Power
Planning authority
Broadland
Planning application reference
20131408
Site area
12.7 ha
Address (REPD)
Land North of Stonehouse Road,Salhouse
Council area (by location)
Broadland
Time to decision
17 weeks
REPD reference
2050

Who decides

ApplicationsBroadlandUK
Decided applications (solar, wind, battery)2210,236
Refused7 (32%)19%
Solar refused4 of 1712%
Onshore wind refused2 of 245%
Battery storage refused1 of 316%
Median time from submission to decision18.3 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land off Belaugh Roadsolar farm12application withdrawn3.4
Belaugh Road Solar Farmsolar farm12application withdrawn3.5
Burgate Solar Farmsolar farm15approved, not built6.7
Scottow Moor - RAF Coltishall Solar Farm (Phase 2)solar farm17.9operational7.9
Scottow Moor - RAF Coltishall Solar Farm (Phase 1)solar farm32operational7.9
Scottow Road Solar Farmsolar farm12.7application withdrawn9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6887, 1.4).