Land off Belaugh Road (12 MW solar farm)

Land off Belaugh Road is a 12 MW solar farm project in Broadland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 21 December 2012; the record was last updated on 26 February 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
application withdrawnstatus in REPD
26 February 2013record last updated
Broadlandcouncil area

Planning timeline

DateStage
23 October 2012Application submitted
21 December 2012Application withdrawn

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
application withdrawn
Record last updated
26 February 2013
Operator or applicant
Trafford Estate Solar Park Ltd
Planning authority
Broadland
Planning application reference
20121424
Address (REPD)
Belaugh Road, Hoveton
Council area (by location)
Broadland
REPD reference
1162

Who decides

ApplicationsBroadlandUK
Decided applications (solar, wind, battery)2210,236
Refused7 (32%)19%
Solar refused4 of 1712%
Onshore wind refused2 of 245%
Battery storage refused1 of 316%
Median time from submission to decision18.3 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Belaugh Road Solar Farmsolar farm12application withdrawn0.5
Salhouse Solar Farmsolar farm5operational3.4
Scottow Moor - RAF Coltishall Solar Farm (Phase 2)solar farm17.9operational4.8
Scottow Moor - RAF Coltishall Solar Farm (Phase 1)solar farm32operational4.8
Scottow Road Solar Farmsolar farm12.7application withdrawn6.2
Burgate Solar Farmsolar farm15approved, not built6.2
Bunn's Hill Solar Parksolar farm5operational8.8
Frog's Loke Solar Farmsolar farm5operational8.8
Carlton Farm Solar farmsolar farm5operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7189, 1.3958).