Hemsby Wind Farm (10 MW)

Hemsby Wind Farm is a 10 MW wind farm project in Great Yarmouth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 23 December 2009; the record was last updated on 5 January 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
refusedstatus in REPD
5 January 2011record last updated
Great Yarmouthcouncil area

Planning timeline

DateStage
8 September 2009Application submitted
23 December 2009Refused by the planning authority

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
refused
Record last updated
5 January 2011
Operator or applicant
Sea & Land Power and Energy Ltd
Planning authority
Great Yarmouth
Planning application reference
06/09/0592/F
Appeal reference
40351
Turbines
4
Address (REPD)
between the villages of Hemsby and Ormesby St Margaret
Council area (by location)
Great Yarmouth
Time to decision
15 weeks
REPD reference
2764

Earlier applications for this site

ApplicationMWSubmittedOutcome
Hemsby Wind Farm1020 August 2007withdrawn 1 December 2007

Who decides

ApplicationsGreat YarmouthUK
Decided applications (solar, wind, battery)1610,236
Refused2 (12%)19%
Solar refused0 of 912%
Onshore wind refused2 of 545%
Battery storage refused0 of 216%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nova Scotia Farm solar parksolar farm13.9operational3.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.687, 1.6799).