Nova Scotia Farm solar park (13.9 MW)

Nova Scotia Farm solar park is a 13.9 MW solar farm project in Great Yarmouth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 3 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.9 MWsolar farm
operationalstatus in REPD
3 January 2017record last updated
Great Yarmouthcouncil area

Planning timeline

DateStage
16 April 2013Application submitted
10 July 2013Planning permission granted
30 November 2013Construction started
31 March 2014Operational

Project details

Technology
solar farm
Capacity
13.9 MW
Status (REPD)
operational
Record last updated
3 January 2017
Operator or applicant
Equitix
Planning authority
Great Yarmouth
Planning application reference
06/13/0180/F
Site area
29.0 ha
Address (REPD)
Nova Scotia Farm, West Caister, Great Yarmouth, Norfolk
Council area (by location)
Great Yarmouth
Time to decision
12 weeks
REPD reference
1328

Who decides

ApplicationsGreat YarmouthUK
Decided applications (solar, wind, battery)1610,236
Refused2 (12%)19%
Solar refused0 of 912%
Onshore wind refused2 of 545%
Battery storage refused0 of 216%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hemsby Wind Farmwind farm10refused3.2
Admiralty Roadbattery storage50approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6618, 1.7012).