West Raynham (49.9 MW solar farm)

West Raynham is a 49.9 MW solar farm project in North Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 9 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
operationalstatus in REPD
9 April 2015record last updated
North Norfolkcouncil area

Planning timeline

DateStage
31 October 2013Application submitted
20 December 2013Planning permission granted
23 September 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
9 April 2015
Operator or applicant
Bluefield Solar
Planning authority
North Norfolk
Planning application reference
PF/13/1166
Site area
91.1 ha
Address (REPD)
Former Airfield, West Raynham, Fakenham, Norfolk
Council area (by location)
North Norfolk
Time to decision
7 weeks
REPD reference
2088

Who decides

ApplicationsNorth NorfolkUK
Decided applications (solar, wind, battery)3610,236
Refused4 (11%)19%
Solar refused2 of 2912%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision13.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shereford Road, West Raynham Estatebattery storage50approved, not built3.0
Claypit Moor Solar Farm (Lexham)solar farm7.9operational5.5
South Creake Solar Farmsolar farm26operational8.1
Chiplowwind farm8.2operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7905, 0.7448).