Energy Projects Near You

Solar, wind and battery projects near King's Lynn (PE32)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE32 (King's Lynn and West Norfolk): 2 are waiting for a planning decision, 2 approved but not yet running, 5 operational. The largest live scheme is The Droves Solar Farm (500 MW solar farm, application submitted on 16 December 2025, no decision recorded), 5.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
2awaiting a decision
2approved, not running
5operational

Projects within 10 km of PE32

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Droves Solar Farmsolar farmsolar farm500application submittedupdated Jun 2026Dec 2025—Jun 2026Breckland5.2
Burntstalk Solar Parksolar farmsolar farm11.5operationalupdated Oct 2014Oct 2012granted Dec 2012Oct 2014Breckland6.1
Swaffham Extensionwind farmwind farm12refusedupdated Dec 2008Apr 2007refused Mar 2008Dec 2008Breckland7.8
Swaffham 1 - Ecotech Wind Parkwind turbinewind turbine1.5operationalupdated Dec 2008Mar 1998granted Feb 1999Dec 2008Breckland8.5
Washpit Drovewind farmwind farm4.7application withdrawnupdated Nov 2015Feb 2014—Nov 2015Breckland8.9
Swaffham Plashes IIwind turbinewind turbine1.8operationalupdated Sep 2004Dec 2001granted Sep 2002Sep 2004Breckland8.9
Field north of Water Treatment Works / Hoggs Drovesolar farmsolar farm1operationalupdated Oct 2022Oct 2018granted May 2021Oct 2022King's Lynn and West Norfolk9.3
Jafa, Great Dunham Solar Photovoltaic Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Sep 2024Oct 2022granted Mar 2023Sep 2024Breckland9.4
Claypit Moor Solar Farm (Lexham)solar farmsolar farm7.9operationalupdated Oct 2014Sep 2012granted Dec 2012Oct 2014Breckland9.6
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Droves Solar Farm Batterybattery storagebattery storage—application submittedupdated Jun 2026Dec 2025—Jun 2026Breckland5.2
Jafa, Great Dunham Solar Photovoltaic Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Sep 2024Oct 2022granted Mar 2023Sep 2024Breckland9.4

Distance from the average position of the PE32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm51130550
Wind farm200010
Wind turbine200200
Battery storage211000

MW in pipeline: pending, approved and under-construction capacity.

How King's Lynn and West Norfolk decides solar, wind and battery applications

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in King's Lynn and West Norfolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE32, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.