Swaffham Extension (12 MW wind farm)
Swaffham Extension is a 12 MW wind farm project in Breckland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 March 2008; the record was last updated on 5 December 2008.
12 MWwind farm
refusedstatus in REPD
5 December 2008record last updated
Brecklandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 27 April 2007 | Application submitted |
| 6 March 2008 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- refused
- Record last updated
- 5 December 2008
- Operator or applicant
- Ecotricity
- Planning authority
- Breckland
- Planning application reference
- 3/07/0314/F
- Turbines
- 6
- Address (REPD)
- East Of West Acre Road, Swaffham, Norfolk
- Council area (by location)
- Breckland
- Time to decision
- 45 weeks
- REPD reference
- 2994
Who decides
| Applications | Breckland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 38 | 10,236 |
| Refused | 7 (18%) | 19% |
| Solar refused | 4 of 28 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 19.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| The Droves Solar Farm | solar farm | 500 | application submitted | 2.7 |
| Home Farm (Swaffham) | solar farm | 12 | application withdrawn | 3.6 |
| Burntstalk Solar Park | solar farm | 11.5 | operational | 3.8 |
| North Pickenham | wind farm | 14.4 | operational | 5.1 |
| Jafa, Great Dunham Solar Photovoltaic Farm & Battery Storage | solar farm | 49.9 | approved, not built | 6.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6628, 0.6809).