Energy Projects Near You

The Droves Solar Farm (500 MW)

The Droves Solar Farm is a 500 MW solar farm project in Breckland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 16 December 2025, no decision recorded; the record was last updated on 26 June 2026. As a nationally significant project, it is decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN0110013).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWsolar farm
application submittedstatus in REPD
26 June 2026record last updated
Brecklandcouncil area

Planning timeline

DateStage
16 December 2025Application submitted

Project details

Technology
solar farm
Capacity
500 MW
Status (REPD)
application submitted
Record last updated
26 June 2026
Operator or applicant
Island Green Power
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN0110013
Site area
840.0 ha
Address (REPD)
Petticoat Drove, South Acre, Breckland
Council area (by location)
Breckland
REPD reference
17560

Who decides

As a nationally significant project, it is decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN0110013). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Burntstalk Solar Parksolar farm11.5operational2.4
Swaffham Extensionwind farm12refused2.7
Home Farm (Swaffham)solar farm12application withdrawn6.3
Jafa, Great Dunham Solar Photovoltaic Farm & Battery Storagesolar farm49.9approved, not built7.2
North Pickenhamwind farm14.4operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6832, 0.6589).