Energy Projects Near You

Solar, wind and battery projects near Swaffham (PE37)

15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE37 (Breckland): 2 are waiting for a planning decision, 4 approved but not yet running, 6 operational. The largest live scheme is The Droves Solar Farm (500 MW solar farm, application submitted on 16 December 2025, no decision recorded), 5.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects within 10 km
2awaiting a decision
4approved, not running
6operational

Projects within 10 km of PE37

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Home Farm (Swaffham)solar farmsolar farm12application withdrawnupdated Sep 2014May 2014—Sep 2014Breckland1.1
Swaffham Plashes IIwind turbinewind turbine1.8operationalupdated Sep 2004Dec 2001granted Sep 2002Sep 2004Breckland1.9
Swaffham 1 - Ecotech Wind Parkwind turbinewind turbine1.5operationalupdated Dec 2008Mar 1998granted Feb 1999Dec 2008Breckland2.1
Washpit Drovewind farmwind farm4.7application withdrawnupdated Nov 2015Feb 2014—Nov 2015Breckland2.2
North Pickenhamwind farmwind farm14.4operationalupdated May 2009Mar 2004granted Oct 2004May 2009Breckland2.5
Swaffham Extensionwind farmwind farm12refusedupdated Dec 2008Apr 2007refused Mar 2008Dec 2008Breckland2.7
North Pickenham Airfieldwind farmwind farm4operationalupdated Mar 2015Sep 2009granted Sep 2010Mar 2015Breckland2.8
The Droves Solar Farmsolar farmsolar farm500application submittedupdated Jun 2026Dec 2025—Jun 2026Breckland5.5
Burntstalk Solar Parksolar farmsolar farm11.5operationalupdated Oct 2014Oct 2012granted Dec 2012Oct 2014Breckland6.1
Jafa, Great Dunham Solar Photovoltaic Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Sep 2024Oct 2022granted Mar 2023Sep 2024Breckland7.4
Huntingfield Solar Farmsolar farmsolar farm4.4operationalupdated Sep 2018Jun 2015granted Sep 2015Sep 2018Breckland10.0
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hamonds High School, Brandon Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Breckland0.8
Nicholas Hamond Academy Solar Panel Canopiessolar farmsolar farm0.2approved, not builtupdated Dec 2023Oct 2023granted Nov 2023Dec 2023Breckland0.8
The Droves Solar Farm Batterybattery storagebattery storage—application submittedupdated Jun 2026Dec 2025—Jun 2026Breckland5.5
Jafa, Great Dunham Solar Photovoltaic Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Sep 2024Oct 2022granted Mar 2023Sep 2024Breckland7.4

Distance from the average position of the PE37 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm61220550
Rooftop solar101000.3
Wind farm400210
Wind turbine200200
Battery storage211000

MW in pipeline: pending, approved and under-construction capacity.

How Breckland decides solar, wind and battery applications

ApplicationsBrecklandUK
Decided applications (solar, wind, battery)3810,236
Refused7 (18%)19%
Solar refused4 of 2812%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Breckland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE37, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.