Solar, wind and battery projects near Thetford (IP26)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP26 (King's Lynn and West Norfolk): 3 are waiting for a planning decision, 5 approved but not yet running, 5 operational. The largest live scheme is Brandon Fields Estate, Brandon Fields (28 MW solar farm, application submitted on 10 June 2025, no decision recorded), 7.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of IP26
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Solar PV Panelssolar farm | solar farm | 15 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Oct 2025 | Nov 2025 | King's Lynn and West Norfolk | 3.3 |
| Hall Farm, West End Northwold Solar Farmsolar farm | solar farm | 10 | operationalupdated Mar 2025 | Dec 2021 | granted Mar 2022 | Mar 2025 | King's Lynn and West Norfolk | 4.2 |
| Hall Farm, West End Northwold Solar Farmbattery storage | battery storage | 7.5 | operationalupdated Mar 2025 | Dec 2021 | granted Mar 2022 | Mar 2025 | King's Lynn and West Norfolk | 4.2 |
| Meadow Farm solar parksolar farm | solar farm | 6 | operationalupdated Jul 2014 | May 2013 | granted Jul 2013 | Jul 2014 | King's Lynn and West Norfolk | 4.4 |
| Reaches Farm Solar Parksolar farm | solar farm | 6.1 | operationalupdated May 2014 | May 2013 | granted Aug 2013 | May 2014 | King's Lynn and West Norfolk | 5.8 |
| Land North Of, Whittington Hilsolar farm | solar farm | 5 | abandonedupdated Mar 2019 | Jun 2015 | granted Oct 2015 | Mar 2019 | Breckland | 6.2 |
| Brandon Fields Estate, Brandon Fieldssolar farm | solar farm | 28 | application submittedupdated Jul 2025 | Jun 2025 | — | Jul 2025 | West Suffolk | 7.4 |
| Toggam Farmsolar farm | solar farm | 12.5 | operationalupdated Aug 2016 | Dec 2012 | granted May 2013 | Aug 2016 | West Suffolk | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Former RAF Methwoldsolar farm | solar farm | 0.3 | application submitted may be out of dateupdated Jan 2021 | Sep 2020 | — | Jan 2021 | King's Lynn and West Norfolk | 2.3 |
| Thetford Road, Pooly Farmsolar farm | solar farm | 0.2 | approved, not builtupdated Jan 2025 | Nov 2024 | granted Jan 2025 | Jan 2025 | King's Lynn and West Norfolk | 4.2 |
| Southery Road Farm, Ploughmans Droverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2024 | Sep 2024 | granted Oct 2024 | Oct 2024 | King's Lynn and West Norfolk | 6.3 |
| Norfolk House, High Streetrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Feb 2026 | Nov 2025 | granted Dec 2025 | Feb 2026 | West Suffolk | 7.0 |
| Brandon Fields Estate, Brandon Fieldsbattery storage | battery storage | — | application submittedupdated Jul 2025 | Jun 2025 | — | Jul 2025 | West Suffolk | 7.4 |
| Towlers Farm, Southery Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | King's Lynn and West Norfolk | 9.0 |
Distance from the average position of the IP26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 2 | 2 | 4 | 0 | 43.5 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 1.2 |
| Battery storage | 2 | 1 | 0 | 1 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How King's Lynn and West Norfolk decides solar, wind and battery applications
| Applications | King's Lynn and West Norfolk | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 60 | 10,236 |
| Refused | 11 (18%) | 19% |
| Solar refused | 5 of 38 | 12% |
| Onshore wind refused | 3 of 6 | 45% |
| Battery storage refused | 3 of 16 | 16% |
| Median time from submission to decision | 14.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
All projects in King's Lynn and West Norfolk
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IP26, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.