Solar, wind and battery projects near Bury St Edmunds (IP28)
15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP28 (West Suffolk): 2 are waiting for a planning decision, 10 approved but not yet running, 2 operational. The largest live scheme is Sunnica Energy Farm (East and West) (500 MW solar farm, approved on 12 July 2024, not yet built), 3.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of IP28
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bay Farmsolar farm | solar farm | 8.1 | operationalupdated Aug 2017 | Aug 2012 | granted Nov 2012 | Aug 2017 | West Suffolk | 2.5 |
| Cavenham Quarry, Cavenham Heathsolar farm | solar farm | 1.3 | approved, not builtupdated Jan 2026 | Aug 2025 | granted Jan 2026 | Jan 2026 | West Suffolk | 2.6 |
| Sunnica Energy Farm (East and West)solar farm | solar farm | 500 | approved, not builtupdated Dec 2024 | Nov 2021 | granted Jul 2024 | Dec 2024 | West Suffolk | 3.1 |
| Sunnica Energy Farm (East and West)battery storage | battery storage | 8.8 | approved, not builtupdated Dec 2024 | Nov 2021 | granted Jul 2024 | Dec 2024 | West Suffolk | 3.1 |
| Icklingham Solar Farmsolar farm | solar farm | 8 | permission expiredupdated Nov 2019 | May 2013 | granted Aug 2013 | Nov 2019 | West Suffolk | 3.6 |
| Lackford Estate Solar Parksolar farm | solar farm | 20.9 | operationalupdated Apr 2014 | Aug 2013 | granted Nov 2013 | Apr 2014 | West Suffolk | 7.4 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Mildenhall Hub, Sheldrick Waysolar farm | solar farm | — | approved, not builtupdated Apr 2026 | Nov 2025 | granted Mar 2026 | Apr 2026 | West Suffolk | 2.2 |
| College Heath Road, Mildenhall - Micro Energy Storage Systembattery storage | battery storage | 0.2 | approved, not builtupdated Jan 2026 | Aug 2025 | granted Dec 2025 | Jan 2026 | West Suffolk | 2.8 |
| J K H Drainage Units, Chiswick Avenuerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 | West Suffolk | 2.8 |
| Hampstead Avenue, Mildenhallrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | West Suffolk | 2.9 |
| Silverline Office Equipment, James Carter Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | West Suffolk | 3.1 |
| Cranhouse, Eriswellsolar farm | solar farm | 0.2 | application submittedupdated Jan 2025 | Dec 2024 | — | Jan 2025 | West Suffolk | 6.1 |
| Tuddenham Road, Higham - Ground Mounted Solar Arraysolar farm | solar farm | 0.3 | approved, not built may be out of dateupdated Jun 2023 | Feb 2022 | granted Jun 2023 | Jun 2023 | West Suffolk | 7.1 |
| Around Eriswell, Eriswellsolar farm | solar farm | 0.3 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | West Suffolk | 8.0 |
| Quotient Bioresearch Limited, Newmarket Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Nov 2025 | Jan 2026 | East Cambridgeshire | 9.9 |
Distance from the average position of the IP28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 2 | 4 | 2 | 0 | 502 |
| Rooftop solar | 4 | 0 | 4 | 0 | 0 | 1.5 |
| Battery storage | 2 | 0 | 2 | 0 | 0 | 9 |
MW in pipeline: pending, approved and under-construction capacity.
How West Suffolk decides solar, wind and battery applications
| Applications | West Suffolk | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 38 | 10,236 |
| Refused | 5 (13%) | 19% |
| Solar refused | 4 of 33 | 12% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 13.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IP28, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.