Solar, wind and battery projects near Ely (CB7)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CB7 (East Cambridgeshire): 2 are waiting for a planning decision, 12 approved but not yet running, 12 operational. The largest live scheme is Wicken Bridleway, Church Road (400 MW battery storage, approved on 8 April 2026, not yet built), 6.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CB7
Projects of 1 MW and more (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Triangle Solar Farm Parksolar farm | solar farm | 12 | operationalupdated Feb 2017 | Jul 2014 | granted Oct 2014 | Feb 2017 | East Cambridgeshire | 3.5 |
| North Angle Farmsolar farm | solar farm | 29.4 | under constructionupdated Dec 2023 | Aug 2020 | granted Nov 2020 | Dec 2023 | East Cambridgeshire | 4.2 |
| Bracks Farmsolar farm | solar farm | 28 | operationalupdated Oct 2023 | Apr 2020 | granted Oct 2021 | Oct 2023 | East Cambridgeshire | 4.6 |
| Wicken Bridleway, Church Roadbattery storage | battery storage | 400 | approved, not builtupdated May 2026 | Mar 2025 | granted Apr 2026 | May 2026 | East Cambridgeshire | 6.2 |
| Goose Hall Solar Farmsolar farm | solar farm | 5 | approved, not built may be out of dateupdated Sep 2021 | Dec 2020 | granted Mar 2021 | Sep 2021 | East Cambridgeshire | 7.1 |
| Burwell Anchor Lane Farm, Newnham Drovesolar farm | solar farm | 50 | approved, not builtupdated May 2026 | Apr 2025 | granted Mar 2026 | May 2026 | East Cambridgeshire | 7.4 |
| Stowbridge Farm - Extension (Phase 2)solar farm | solar farm | 10 | operationalupdated May 2015 | Jul 2014 | granted Nov 2014 | May 2015 | East Cambridgeshire | 7.5 |
| Goosehall Solar Farmsolar farm | solar farm | 39.5 | operationalupdated Dec 2021 | Jul 2015 | granted Nov 2015 | Dec 2021 | East Cambridgeshire | 7.5 |
| Stowbridge Farm - Extension (Phase 1)solar farm | solar farm | 10 | operationalupdated May 2015 | Aug 2013 | granted Mar 2014 | May 2015 | East Cambridgeshire | 7.6 |
| Breach Farm Solar farmsolar farm | solar farm | 67 | operationalupdated Apr 2026 | Apr 2021 | granted Dec 2021 | Apr 2026 | East Cambridgeshire | 7.7 |
| Stowbridge Farmsolar farm | solar farm | 24 | operationalupdated Feb 2015 | Sep 2012 | granted Dec 2012 | Feb 2015 | East Cambridgeshire | 8.2 |
| Anchor Lane, Burwellbattery storage | battery storage | 50 | approved, not builtupdated Jun 2025 | Jul 2024 | granted May 2025 | Jun 2025 | East Cambridgeshire | 8.2 |
| Chittering Solar Farmsolar farm | solar farm | 5 | operationalupdated Oct 2012 | Dec 2010 | granted Mar 2011 | Oct 2012 | East Cambridgeshire | 8.6 |
| Burwell Solar Farmsolar farm | solar farm | 49.9 | under constructionupdated Jan 2022 | May 2020 | granted Nov 2020 | Jan 2022 | East Cambridgeshire | 8.6 |
| Chittering Solar Farm - extension 2solar farm | solar farm | 9.6 | approved, not built may be out of dateupdated May 2019 | Jun 2014 | granted Jun 2015 | May 2019 | East Cambridgeshire | 8.6 |
| Chittering Solar Farm Extensionsolar farm | solar farm | 6.3 | operationalupdated Apr 2013 | Jul 2012 | granted Oct 2012 | Apr 2013 | East Cambridgeshire | 8.9 |
| Burwellbattery storage | battery storage | 50 | operationalupdated Mar 2024 | Dec 2017 | granted Apr 2018 | Mar 2024 | East Cambridgeshire | 9.1 |
| Long Barrow Solar Farm Projectsolar farm | solar farm | 49.9 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | East Cambridgeshire | 9.1 |
| Weirs Drove, Burwellbattery storage | battery storage | 30 | application submitted may be out of dateupdated Jul 2021 | May 2021 | — | Jul 2021 | East Cambridgeshire | 9.5 |
| Land Southwest of Hightown Drove, Burwellbattery storage | battery storage | 90 | refusedupdated May 2026 | Jul 2025 | refused Mar 2026 | May 2026 | East Cambridgeshire | 9.7 |
| Forest Heath Solar Farmsolar farm | solar farm | 5 | operationalupdated Mar 2015 | Nov 2012 | granted Jan 2013 | Mar 2015 | East Cambridgeshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Mettleham Farm Centre, Hasse Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | East Cambridgeshire | 2.4 |
| The Cloistersrooftop solar | rooftop solar | — | approved, not builtupdated Jul 2023 | Apr 2023 | granted Jun 2023 | Jul 2023 | East Cambridgeshire | 6.1 |
| Cambridge Commodities, Lancaster Way Business Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | East Cambridgeshire | 7.4 |
| Breach Farm Solar farmbattery storage | battery storage | 0.7 | operationalupdated Apr 2026 | Apr 2021 | granted Dec 2021 | Apr 2026 | East Cambridgeshire | 7.7 |
| Quotient Bioresearch Limited, Newmarket Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Nov 2025 | Jan 2026 | East Cambridgeshire | 8.6 |
| The Harbour School, Station Road Solar Panels & ASHProoftop solar | rooftop solar | 0.9 | approved, not built may be out of dateupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 | East Cambridgeshire | 9.9 |
Distance from the average position of the CB7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 16 | 1 | 5 | 10 | 0 | 194 |
| Rooftop solar | 5 | 0 | 5 | 0 | 0 | 1.5 |
| Battery storage | 6 | 1 | 2 | 2 | 1 | 480 |
MW in pipeline: pending, approved and under-construction capacity.
How East Cambridgeshire decides solar, wind and battery applications
| Applications | East Cambridgeshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 1 (3%) | 19% |
| Solar refused | 0 of 22 | 12% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 15.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in East Cambridgeshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CB7, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.