Solar, wind and battery projects near Cambridge (CB25)
36 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CB25 (East Cambridgeshire): 6 are waiting for a planning decision, 14 approved but not yet running, 15 operational. The largest live scheme is Newmarket Road, Bottisham (50 MW battery storage, approved on 21 December 2023, not yet built), 5.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CB25
Projects of 1 MW and more (27)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Burwell Solar Farmsolar farm | solar farm | 49.9 | under constructionupdated Jan 2022 | May 2020 | granted Nov 2020 | Jan 2022 | East Cambridgeshire | 4.2 |
| Anchor Lane, Burwellbattery storage | battery storage | 50 | approved, not builtupdated Jun 2025 | Jul 2024 | granted May 2025 | Jun 2025 | East Cambridgeshire | 4.3 |
| Weirs Drove, Burwellbattery storage | battery storage | 30 | application submitted may be out of dateupdated Jul 2021 | May 2021 | — | Jul 2021 | East Cambridgeshire | 4.4 |
| Reach Roadbattery storage | battery storage | 49.9 | approved, not builtupdated Jun 2020 | May 2020 | granted Jul 2020 | Jun 2020 | East Cambridgeshire | 4.5 |
| Burwellbattery storage | battery storage | 50 | operationalupdated Mar 2024 | Dec 2017 | granted Apr 2018 | Mar 2024 | East Cambridgeshire | 4.7 |
| Land Southwest of Hightown Drove, Burwellbattery storage | battery storage | 90 | refusedupdated May 2026 | Jul 2025 | refused Mar 2026 | May 2026 | East Cambridgeshire | 5.2 |
| Goosehall Solar Farmsolar farm | solar farm | 39.5 | operationalupdated Dec 2021 | Jul 2015 | granted Nov 2015 | Dec 2021 | East Cambridgeshire | 5.2 |
| Burwell Anchor Lane Farm, Newnham Drovesolar farm | solar farm | 50 | approved, not builtupdated May 2026 | Apr 2025 | granted Mar 2026 | May 2026 | East Cambridgeshire | 5.3 |
| Newmarket Road, Bottishambattery storage | battery storage | 50 | approved, not builtupdated Feb 2026 | Nov 2022 | granted Dec 2023 | Feb 2026 | East Cambridgeshire | 5.4 |
| Newmarket Road, Bottishamsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Nov 2022 | granted Dec 2023 | Feb 2026 | East Cambridgeshire | 5.4 |
| Long Barrow Solar Farm Projectsolar farm | solar farm | 49.9 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | East Cambridgeshire | 5.5 |
| Goose Hall Solar Farmsolar farm | solar farm | 5 | approved, not built may be out of dateupdated Sep 2021 | Dec 2020 | granted Mar 2021 | Sep 2021 | East Cambridgeshire | 5.9 |
| Chittering Solar Farm - extension 2solar farm | solar farm | 9.6 | approved, not built may be out of dateupdated May 2019 | Jun 2014 | granted Jun 2015 | May 2019 | East Cambridgeshire | 6.3 |
| Ely Road Waste Management Parksolar farm | solar farm | 1.1 | operationalupdated Feb 2022 | Nov 2019 | granted Mar 2020 | Feb 2022 | South Cambridgeshire | 6.4 |
| Chittering Solar Farm Extensionsolar farm | solar farm | 6.3 | operationalupdated Apr 2013 | Jul 2012 | granted Oct 2012 | Apr 2013 | East Cambridgeshire | 6.4 |
| Exningsolar farm | solar farm | 29.9 | operationalupdated Feb 2017 | Oct 2013 | granted Jul 2014 | Feb 2017 | East Cambridgeshire | 6.6 |
| Chittering Solar Farmsolar farm | solar farm | 5 | operationalupdated Oct 2012 | Dec 2010 | granted Mar 2011 | Oct 2012 | East Cambridgeshire | 6.7 |
| Low Fen, Drove Way Solar Farmsolar farm | solar farm | 50 | application submittedupdated May 2025 | Mar 2025 | — | May 2025 | South Cambridgeshire | 7.0 |
| Breach Farm Solar farmsolar farm | solar farm | 67 | operationalupdated Apr 2026 | Apr 2021 | granted Dec 2021 | Apr 2026 | East Cambridgeshire | 7.3 |
| Bracks Farmsolar farm | solar farm | 28 | operationalupdated Oct 2023 | Apr 2020 | granted Oct 2021 | Oct 2023 | East Cambridgeshire | 7.8 |
| Stowbridge Farmsolar farm | solar farm | 24 | operationalupdated Feb 2015 | Sep 2012 | granted Dec 2012 | Feb 2015 | East Cambridgeshire | 7.9 |
| Stowbridge Farm - Extension (Phase 1)solar farm | solar farm | 10 | operationalupdated May 2015 | Aug 2013 | granted Mar 2014 | May 2015 | East Cambridgeshire | 7.9 |
| North Angle Farmsolar farm | solar farm | 29.4 | under constructionupdated Dec 2023 | Aug 2020 | granted Nov 2020 | Dec 2023 | East Cambridgeshire | 8.0 |
| Stowbridge Farm - Extension (Phase 2)solar farm | solar farm | 10 | operationalupdated May 2015 | Jul 2014 | granted Nov 2014 | May 2015 | East Cambridgeshire | 8.2 |
| Triangle Solar Farm Parksolar farm | solar farm | 12 | operationalupdated Feb 2017 | Jul 2014 | granted Oct 2014 | Feb 2017 | East Cambridgeshire | 8.6 |
| Great Wilbraham Solar Farmsolar farm | solar farm | 38.1 | operationalupdated Apr 2015 | Jan 2014 | granted Jul 2014 | Apr 2015 | South Cambridgeshire | 8.6 |
| Forest Heath Solar Farmsolar farm | solar farm | 5 | operationalupdated Mar 2015 | Nov 2012 | granted Jan 2013 | Mar 2015 | East Cambridgeshire | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Cambridge Waste Management Park Solar Farmsolar farm | solar farm | — | approved, not builtupdated Dec 2025 | Jun 2025 | granted Nov 2025 | Dec 2025 | South Cambridgeshire | 6.3 |
| Low Fen, Drove Waybattery storage | battery storage | — | application submittedupdated May 2025 | Mar 2025 | — | May 2025 | South Cambridgeshire | 7.0 |
| Breach Farm Solar farmbattery storage | battery storage | 0.7 | operationalupdated Apr 2026 | Apr 2021 | granted Dec 2021 | Apr 2026 | East Cambridgeshire | 7.3 |
| CRM Surgical, 1 Evolution Business Parkrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jul 2022 | Feb 2022 | granted Apr 2022 | Jul 2022 | South Cambridgeshire | 7.8 |
| Levidian Nanosystems, Levidian Technology Centrerooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Jan 2023 | Dec 2022 | — | Jan 2023 | Cambridge | 8.8 |
| Coldhams Business Park, Norman Wayrooftop solar | rooftop solar | 0.2 | application submitted | Apr 2026 | — | — | Cambridge | 9.4 |
| Coldhams Business Park, Norman Wayrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2023 | Nov 2023 | granted Mar 2024 | Dec 2023 | Cambridge | 9.4 |
| Sewage Pumping Station - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Sep 2024 | Oct 2024 | South Cambridgeshire | 9.6 |
| New Road, Impingtonrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | South Cambridgeshire | 9.7 |
Distance from the average position of the CB25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 22 | 2 | 7 | 13 | 0 | 294 |
| Rooftop solar | 5 | 2 | 3 | 0 | 0 | 2 |
| Battery storage | 9 | 2 | 4 | 2 | 1 | 180 |
MW in pipeline: pending, approved and under-construction capacity.
How East Cambridgeshire decides solar, wind and battery applications
| Applications | East Cambridgeshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 1 (3%) | 19% |
| Solar refused | 0 of 22 | 12% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 15.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in East Cambridgeshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CB25, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.