Energy Projects Near You

Forest Heath Solar Farm (5 MW)

Forest Heath Solar Farm is a 5 MW solar farm project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 February 2014; the record was last updated on 17 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
17 March 2015record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
7 November 2012Application submitted
2 January 2013Planning permission granted
4 February 2014Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
17 March 2015
Operator or applicant
Munich RE
Planning authority
West Suffolk
Planning application reference
F/2012/0655/FUL
Address (REPD)
Fordham Road, Newmarket, Suffolk
Council area (by location)
East Cambridgeshire
Time to decision
8 weeks
REPD reference
1736

Who decides

ApplicationsWest SuffolkUK
Decided applications (solar, wind, battery)3810,236
Refused5 (13%)19%
Solar refused4 of 3312%
Battery storage refused1 of 516%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Breach Farm Solar farmsolar farm67operational3.2
Long Barrow Solar Farm Projectsolar farm49.9application submitted4.2
Exningsolar farm29.9operational4.4
Land Southwest of Hightown Drove, Burwellbattery storage90refused4.4
Reach Roadbattery storage49.9approved, not built5.0
Burwellbattery storage50operational5.1
Goose Hall Solar Farmsolar farm5approved, not built5.2
Weirs Drove, Burwellbattery storage30application submitted5.3
Burwell Anchor Lane Farm, Newnham Drovesolar farm50approved, not built5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2794, 0.3914).