Reach Road (49.9 MW battery storage)

Reach Road is a 49.9 MW battery storage project in East Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 July 2020, not yet built; the record was last updated on 30 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
30 June 2020record last updated
East Cambridgeshirecouncil area

Planning timeline

DateStage
20 May 2020Application submitted
15 July 2020Planning permission granted

Project details

Technology
battery storage (co-located with re)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
30 June 2020
Operator or applicant
UK Power Networks
Planning authority
East Cambridgeshire
Planning application reference
20/00655/SON
Address (REPD)
Armtrac, 70 Reach Road, Burwell, Cambridge, Cambridgeshire
Council area (by location)
East Cambridgeshire
Time to decision
8 weeks
REPD reference
7906

Who decides

ApplicationsEast CambridgeshireUK
Decided applications (solar, wind, battery)3010,236
Refused1 (3%)19%
Solar refused0 of 2212%
Battery storage refused1 of 816%
Median time from submission to decision15.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Weirs Drove, Burwellbattery storage30application submitted0.6
Land Southwest of Hightown Drove, Burwellbattery storage90refused0.7
Burwellbattery storage50operational1.0
Long Barrow Solar Farm Projectsolar farm49.9application submitted1.2
Burwell Solar Farmsolar farm49.9under construction1.9
Anchor Lane, Burwellbattery storage50approved, not built2.3
Goosehall Solar Farmsolar farm39.5operational2.7
Burwell Anchor Lane Farm, Newnham Drovesolar farm50approved, not built2.7
Goose Hall Solar Farmsolar farm5approved, not built2.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2698, 0.3189).