Energy Projects Near You

Solar, wind and battery projects near Newmarket (CB8)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CB8 (West Suffolk): 2 are waiting for a planning decision, 2 approved but not yet running, 5 operational. The largest live scheme is Long Barrow Solar Farm Project (49.9 MW solar farm, application submitted on 16 July 2025, no decision recorded), 8.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
2awaiting a decision
2approved, not running
5operational

Projects within 10 km of CB8

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Exningsolar farmsolar farm29.9operationalupdated Feb 2017Oct 2013granted Jul 2014Feb 2017East Cambridgeshire5.9
Forest Heath Solar Farmsolar farmsolar farm5operationalupdated Mar 2015Nov 2012granted Jan 2013Mar 2015East Cambridgeshire6.0
Land Southwest of Hightown Drove, Burwellbattery storagebattery storage90refusedupdated May 2026Jul 2025refused Mar 2026May 2026East Cambridgeshire8.3
Long Barrow Solar Farm Projectsolar farmsolar farm49.9application submittedupdated Aug 2025Jul 2025—Aug 2025East Cambridgeshire8.6
Reach Roadbattery storagebattery storage49.9approved, not builtupdated Jun 2020May 2020granted Jul 2020Jun 2020East Cambridgeshire8.6
Breach Farm Solar farmsolar farmsolar farm67operationalupdated Apr 2026Apr 2021granted Dec 2021Apr 2026East Cambridgeshire8.7
Weirs Drove, Burwellbattery storagebattery storage30application submitted may be out of dateupdated Jul 2021May 2021—Jul 2021East Cambridgeshire9.2
Burwellbattery storagebattery storage50operationalupdated Mar 2024Dec 2017granted Apr 2018Mar 2024East Cambridgeshire9.3
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Quotient Bioresearch Limited, Newmarket Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Sep 2025granted Nov 2025Jan 2026East Cambridgeshire7.4
Breach Farm Solar farmbattery storagebattery storage0.7operationalupdated Apr 2026Apr 2021granted Dec 2021Apr 2026East Cambridgeshire8.7

Distance from the average position of the CB8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4103049.9
Rooftop solar101000.2
Battery storage5112179.9

MW in pipeline: pending, approved and under-construction capacity.

How West Suffolk decides solar, wind and battery applications

ApplicationsWest SuffolkUK
Decided applications (solar, wind, battery)3810,236
Refused5 (13%)19%
Solar refused4 of 3312%
Battery storage refused1 of 516%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in West Suffolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CB8, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.