Solar, wind and battery projects near Haverhill (CB9)
13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CB9 (West Suffolk): 1 is waiting for a planning decision, 9 approved but not yet running, 2 operational. The largest live scheme is Surmer Hall, Church Walk Solar Farm & Battery Storage (36 MW solar farm, approved on 4 December 2024, not yet built), 4.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CB9
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Rookwood Way Solar Farmsolar farm | solar farm | 2 | operationalupdated May 2024 | Feb 2023 | granted Jun 2023 | May 2024 | West Suffolk | 0.9 |
| Surmer Hall, Church Walk Solar Farm & Battery Storagesolar farm | solar farm | 36 | approved, not builtupdated Feb 2026 | Nov 2023 | granted Dec 2024 | Feb 2026 | Braintree | 4.0 |
| Surmer Hall, Church Walk Solar Farm & Battery Storagebattery storage | battery storage | 22 | approved, not builtupdated Feb 2026 | Nov 2023 | granted Dec 2024 | Feb 2026 | Braintree | 4.0 |
| Water Hall Farm, Waterhall Road Solar Farmsolar farm | solar farm | 35 | approved, not builtupdated Feb 2026 | Jul 2023 | granted Jul 2025 | Feb 2026 | West Suffolk | 4.1 |
| Burton Endsolar farm | solar farm | 1.5 | refusedupdated Jun 2023 | Jun 2020 | refused Dec 2021 | Jun 2023 | South Cambridgeshire | 6.3 |
| Broxted Solar Farm (Stradishall Airfield)solar farm | solar farm | 31.6 | operationalupdated Apr 2014 | Sep 2012 | granted Dec 2012 | Apr 2014 | West Suffolk | 7.5 |
Smaller schemes under 1 MW, mostly rooftop solar (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Herbert Retail, Rookwood Wayrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | West Suffolk | 0.8 |
| Samuel Ward Academyrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Nov 2025 | Jan 2026 | West Suffolk | 0.8 |
| Homefield Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Aug 2024 | Apr 2024 | granted Aug 2024 | Aug 2024 | West Suffolk | 1.4 |
| Sainsburys Superstore, Haycocks Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | West Suffolk | 2.2 |
| Haverhill Road, Little Wratting - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | West Suffolk | 2.6 |
| Streetly Hall Farm, Webbs Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | South Cambridgeshire | 7.2 |
| Chipley Abbey Farm, Gosland Greenwind turbine | wind turbine | — | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | West Suffolk | 10.0 |
Distance from the average position of the CB9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 0 | 2 | 2 | 1 | 71 |
| Rooftop solar | 4 | 0 | 4 | 0 | 0 | 0.7 |
| Wind turbine | 1 | 1 | 0 | 0 | 0 | 0 |
| Battery storage | 3 | 0 | 3 | 0 | 0 | 22.4 |
MW in pipeline: pending, approved and under-construction capacity.
How West Suffolk decides solar, wind and battery applications
| Applications | West Suffolk | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 38 | 10,236 |
| Refused | 5 (13%) | 19% |
| Solar refused | 4 of 33 | 12% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 13.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.