Solar, wind and battery projects near Cambridge (CB21)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CB21 (South Cambridgeshire): 8 approved but not yet running, 2 operational. The largest live scheme is Newmarket Road, Bottisham (50 MW battery storage, approved on 21 December 2023, not yet built), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CB21
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Little Linton Farmwind farm | wind farm | 16 | refused on appealupdated Sep 2011 | Mar 2009 | refused Jun 2009 | Sep 2011 | South Cambridgeshire | 2.9 |
| Wadlow Wind Farmwind farm | wind farm | 26 | operationalupdated Sep 2016 | May 2006 | granted Nov 2009 | Sep 2016 | South Cambridgeshire | 4.8 |
| Great Wilbraham Solar Farmsolar farm | solar farm | 38.1 | operationalupdated Apr 2015 | Jan 2014 | granted Jul 2014 | Apr 2015 | South Cambridgeshire | 6.3 |
| Burton Endsolar farm | solar farm | 1.5 | refusedupdated Jun 2023 | Jun 2020 | refused Dec 2021 | Jun 2023 | South Cambridgeshire | 6.8 |
| Sawston Solar Farm (Land North of Dales Manor Business Park)solar farm | solar farm | 14 | refused on appealupdated Jun 2016 | Oct 2014 | refused Dec 2014 | Jun 2016 | South Cambridgeshire | 6.8 |
| Chesterford Park - Green Energy Hubsolar farm | solar farm | 2.8 | approved, not built may be out of dateupdated Sep 2021 | Sep 2021 | granted Dec 2022 | Sep 2021 | Uttlesford | 8.1 |
| Butlers Farmsolar farm | solar farm | 7.7 | refused on appealupdated Apr 2016 | Sep 2014 | refused Mar 2015 | Apr 2016 | Uttlesford | 9.5 |
| Newmarket Road, Bottishambattery storage | battery storage | 50 | approved, not builtupdated Feb 2026 | Nov 2022 | granted Dec 2023 | Feb 2026 | East Cambridgeshire | 9.8 |
| Newmarket Road, Bottishamsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Nov 2022 | granted Dec 2023 | Feb 2026 | East Cambridgeshire | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Dalehead Foods, Lintonrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | South Cambridgeshire | 2.9 |
| Grain Stores, West Wrattingsolar farm | solar farm | — | approved, not builtupdated Sep 2025 | Apr 2025 | granted Sep 2025 | Sep 2025 | South Cambridgeshire | 4.0 |
| Streetly Hall Farm, Webbs Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | South Cambridgeshire | 4.7 |
| Chesterford Park - Green Energy Hubbattery storage | battery storage | — | approved, not built may be out of dateupdated Sep 2021 | Sep 2021 | granted Dec 2022 | Sep 2021 | Uttlesford | 8.4 |
| Sainsburys Superstore, Haycocks Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | West Suffolk | 9.7 |
Distance from the average position of the CB21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 3 | 1 | 3 | 52.7 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 1.4 |
| Wind farm | 2 | 0 | 0 | 1 | 1 | 0 |
| Battery storage | 2 | 0 | 2 | 0 | 0 | 50 |
MW in pipeline: pending, approved and under-construction capacity.
How South Cambridgeshire decides solar, wind and battery applications
| Applications | South Cambridgeshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 48 | 10,236 |
| Refused | 10 (21%) | 19% |
| Solar refused | 6 of 40 | 12% |
| Onshore wind refused | 4 of 5 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 17.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 1 | — |
All projects in South Cambridgeshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CB21, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.