Butlers Farm (7.7 MW solar farm)

Butlers Farm is a 7.7 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 22 March 2016; the record was last updated on 4 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.7 MWsolar farm
refused on appealstatus in REPD
4 April 2016record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
19 September 2014Application submitted
16 March 2015Refused by the planning authority
4 November 2015Appeal lodged
22 March 2016Appeal refused

Project details

Technology
solar farm
Capacity
7.7 MW
Status (REPD)
refused on appeal
Record last updated
4 April 2016
Operator or applicant
Push Energy
Planning authority
Uttlesford
Planning application reference
UTT/14/2755/FUL
Appeal reference
APP/C1570/W/15/3132170
Site area
7.6 ha
Address (REPD)
Butlers Farm, Butlers Lane, Saffron, Walden, Essex
Council area (by location)
Uttlesford
Time to decision
25 weeks
REPD reference
4824

Earlier applications for this site

ApplicationMWSubmittedOutcome
Butlers Farm UTT/13/2889/FUL9.31 November 2013refused 30 January 2014

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Long Meadow Solar Farmsolar farm19operational4.0
Little Linton Farmwind farm16refused on appeal6.8
Abbey Farmsolar farm5application withdrawn9.2
Rectory Farmsolar farm5application withdrawn9.4
Thaxted Solar farmsolar farm40approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0427, 0.274).