Thaxted Solar farm (40 MW)

Thaxted Solar farm is a 40 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 September 2022, not yet built; the record was last updated on 17 January 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
17 January 2024record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
8 June 2021Application submitted
29 September 2022Planning permission granted
28 March 2023Appeal lodged
18 December 2023Appeal allowed
18 December 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
17 January 2024
Operator or applicant
Low Carbon Limited
Planning authority
Uttlesford
Planning application reference
UTT/21/1833/FUL
Appeal reference
23/00029/REF
Site area
52.4 ha
Address (REPD)
Land West Of Thaxted
Council area (by location)
Uttlesford
Time to decision
68 weeks
Contracts for Difference
AR6
Name in REPD
Thaxted - Solar farm
REPD reference
8475

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Terriers Farmsolar farm44operational3.0
Spriggs Farmsolar farm12operational3.3
Hyde Farmsolar farm10.8operational4.8
Long Meadow Solar Farmsolar farm19operational5.8
Tye Green Farmsolar farm14.9application withdrawn8.2
Stanstead Solar Projectsolar farm14.3under construction8.9
Butlers Farmsolar farm7.7refused on appeal9.7
Tooleys Farmsolar farm5.3operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9603, 0.3213).