Stanstead Solar Project (14.3 MW)

Stanstead Solar Project is a 14.3 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 January 2025; the record was last updated on 3 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.3 MWsolar farm
under constructionstatus in REPD
3 March 2025record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
1 June 2022Application submitted
24 August 2022Planning permission granted
24 August 2022Secretary of State granted
1 January 2025Construction started

Project details

Technology
solar farm
Capacity
14.3 MW
Status (REPD)
under construction
Record last updated
3 March 2025
Operator or applicant
Manchester Airport Group Plc
Planning authority
Uttlesford
Planning application reference
S62A/22/0000004
Site area
22.5 ha
Address (REPD)
E/O Coopers End Road
Council area (by location)
Uttlesford
Time to decision
12 weeks
REPD reference
9503

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tye Green Farmsolar farm14.9application withdrawn1.9
Parsonage Farm Solar PV Farm & Battery Storagesolar farm30approved, not built4.5
Merks Hill Farm, Braintree Road Solar Farmsolar farm12application submitted7.8
Solar Farm at W/O A120 Chelmsford Roadsolar farm9.9under construction8.2
Hadham Roadbattery storage10permission expired8.7
Tooleys Farmsolar farm5.3operational8.8
Thaxted Solar farmsolar farm40approved, not built8.9
Maggots End Road, Berden Solar Farm & Battery Storagesolar farm49.9refused9.2
Wickham Hall Estate Solar Photovoltaic Farmsolar farm20approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8879, 0.2657).