Solar Farm at W/O A120 Chelmsford Road (9.9 MW)

Solar Farm at W/O A120 Chelmsford Road is a 9.9 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction; the record was last updated on 18 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.9 MWsolar farm
under constructionstatus in REPD
18 June 2025record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
12 September 2023Application submitted
4 July 2024Planning permission granted

Project details

Technology
solar farm
Capacity
9.9 MW
Status (REPD)
under construction
Record last updated
18 June 2025
Operator or applicant
Dunmow Solar Limited
Planning authority
Uttlesford
Planning application reference
UTT/23/2136/FUL
Site area
6.9 ha
Address (REPD)
W/O A120 Chelmsford Road, Dunmow
Council area (by location)
Uttlesford
Time to decision
42 weeks
Name in REPD
Dunmow Solar Farm, Chelmsford Road - Solar Farm
REPD reference
14930

Earlier applications for this site

ApplicationMWSubmittedOutcome
Bumpstead Hill UTT/15/2318/FUL514 August 2015replaced by a revised application

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Merks Hill Farm, Braintree Road Solar Farmsolar farm12application submitted1.1
Tooleys Farmsolar farm5.3operational2.7
Stanstead Solar Projectsolar farm14.3under construction8.2
Drapers Farm Solar Parksolar farm6operational8.3
Felsted School Road Solar Photovoltaic Farm & Battery storagesolar farm49.9approved, not built9.0
Tye Green Farmsolar farm14.9application withdrawn9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8631, 0.3782).