Energy Projects Near You

Tye Green Farm (14.9 MW solar farm)

Tye Green Farm is a 14.9 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 25 September 2014; the record was last updated on 16 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.9 MWsolar farm
application withdrawnstatus in REPD
16 August 2017record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
4 July 2014Application submitted
25 September 2014Application withdrawn

Project details

Technology
solar farm
Capacity
14.9 MW
Status (REPD)
application withdrawn
Record last updated
16 August 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
Uttlesford
Planning application reference
UTT/14/1916/FUL
Site area
26.6 ha
Address (REPD)
Tye Green Farm Elsenham Elsenham Bishops Stortford
Council area (by location)
Uttlesford
REPD reference
1829

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Stanstead Solar Projectsolar farm14.3under construction1.9
Parsonage Farm Solar PV Farm & Battery Storagesolar farm30approved, not built3.6
Maggots End Road, Berden Solar Farm & Battery Storagesolar farm49.9refused7.4
Hadham Roadbattery storage10permission expired7.7
Thaxted Solar farmsolar farm40approved, not built8.2
Wickham Hall Estatebattery storage10approved, not built8.5
Wickham Hall Estate Solar Photovoltaic Farmsolar farm20approved, not built8.5
Berden Hall Solar Farmsolar farm56approved, not built9.0
Wickham Hall Estate Solar Photovoltaic Farmsolar farm35approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9015, 0.2484).