Wickham Hall Estate Solar Photovoltaic Farm (20 MW)

Wickham Hall Estate Solar Photovoltaic Farm is a 20 MW solar farm project in East Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 September 2024, not yet built; the record was last updated on 23 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtstatus in REPD
23 February 2026record last updated
East Hertfordshirecouncil area

Planning timeline

DateStage
26 June 2024Application submitted
13 September 2024Planning permission granted
13 September 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
23 February 2026
Operator or applicant
Endurance Energy Wickham Hall Limited
Planning authority
Uttlesford
Planning application reference
UTT/24/1417/PINS
Site area
32.9 ha
Address (REPD)
The North-West Of Bishops Stortford Farnham Road Farnham
Council area (by location)
East Hertfordshire
Time to decision
11 weeks
REPD reference
15880

Recorded together with Wickham Hall Estate (10 MW battery storage, approved, not built).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Wickham Hall Estate Solar Photovoltaic Farm UTT/21/3108/FUL—30 November 2021refused 19 April 2022

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Wickham Hall Estate Solar Photovoltaic Farmsolar farm35approved, not built0.7
Hadham Roadbattery storage10permission expired0.9
Maggots End Road, Berden Solar Farm & Battery Storagesolar farm49.9refused4.7
Parsonage Farm Solar PV Farm & Battery Storagesolar farm30approved, not built5.0
Greens Farmbattery storage50approved, not built5.1
Berden Hall Solar Farmsolar farm56approved, not built5.5
Pelhambattery storage49operational5.5
Stocking Pelhambattery storage50refused5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8878, 0.127).