Parsonage Farm Solar PV Farm & Battery Storage (30 MW)

Parsonage Farm Solar PV Farm & Battery Storage is a 30 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 January 2026, not yet built; the record was last updated on 3 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
3 March 2026record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
21 July 2025Application submitted
29 January 2026Planning permission granted
29 January 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
3 March 2026
Operator or applicant
Trilogy Logistics REIT Limited
Planning authority
Essex
Planning application reference
UTT/25/1742/FUL
Site area
47.9 ha
Address (REPD)
Parsonage Farm, Forest Hall Road, Stansted
Council area (by location)
Uttlesford
Time to decision
27 weeks
Name in REPD
Parsonage Farm - Solar PV Farm & Battery Storage
REPD reference
19353

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tye Green Farmsolar farm14.9application withdrawn3.6
Hadham Roadbattery storage10permission expired4.2
Stanstead Solar Projectsolar farm14.3under construction4.5
Wickham Hall Estate Solar Photovoltaic Farmsolar farm20approved, not built5.0
Wickham Hall Estatebattery storage10approved, not built5.0
Maggots End Road, Berden Solar Farm & Battery Storagesolar farm49.9refused5.6
Wickham Hall Estate Solar Photovoltaic Farmsolar farm35approved, not built5.6
Berden Hall Solar Farmsolar farm56approved, not built7.2
Greens Farmbattery storage50approved, not built7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8887, 0.2004).