Solar, wind and battery projects near Sawbridgeworth (CM21)
28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM21 (East Hertfordshire): 2 are waiting for a planning decision, 23 approved but not yet running. The largest live scheme is East End Solar Farm (49.9 MW solar farm, approved on 3 May 2024, not yet built), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CM21
Projects of 1 MW and more (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Poundland Distribution Centrerooftop solar | rooftop solar | 1.5 | approved, not built may be out of dateupdated Jun 2022 | Jun 2022 | granted Jul 2022 | Jun 2022 | Harlow | 7.1 |
| Hadham Roadbattery storage | battery storage | 10 | permission expiredupdated Sep 2020 | Dec 2017 | — | Sep 2020 | East Hertfordshire | 8.1 |
| Wickham Hall Estate Solar Photovoltaic Farmsolar farm | solar farm | 20 | approved, not builtupdated Feb 2026 | Jun 2024 | granted Sep 2024 | Feb 2026 | East Hertfordshire | 8.5 |
| Wickham Hall Estatebattery storage | battery storage | 10 | approved, not builtupdated Feb 2026 | Jun 2024 | granted Sep 2024 | Feb 2026 | East Hertfordshire | 8.5 |
| East End Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Aug 2022 | granted May 2024 | Feb 2026 | Epping Forest | 8.5 |
| Wickham Hall Estate Solar Photovoltaic Farmsolar farm | solar farm | 35 | approved, not builtupdated Feb 2026 | Nov 2021 | granted Dec 2023 | Feb 2026 | East Hertfordshire | 9.0 |
| Parsonage Farm Solar PV Farm & Battery Storagesolar farm | solar farm | 30 | approved, not builtupdated Mar 2026 | Jul 2025 | granted Jan 2026 | Mar 2026 | Uttlesford | 9.3 |
Smaller schemes under 1 MW, mostly rooftop solar (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Gates Of Harlow, Edinburgh Waysolar farm | solar farm | 0.2 | approved, not builtupdated Apr 2022 | Apr 2022 | granted May 2022 | Apr 2022 | Harlow | 3.0 |
| Edinburgh Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Harlow | 3.2 |
| Calder House, Central Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Harlow | 3.5 |
| West Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2026 | Mar 2026 | granted Jun 2026 | Jul 2026 | Harlow | 3.8 |
| Haslemere Industrial Estate, Pig Lanerooftop solar | rooftop solar | 0.3 | refusedupdated Jun 2023 | Jun 2023 | refused Jul 2023 | Jun 2023 | East Hertfordshire | 5.0 |
| Harlow Leisurezone, Second Avenuerooftop solar | rooftop solar | 0.7 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | Harlow | 5.8 |
| Herts and Essex Sports Centre, Beldams Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2024 | Oct 2024 | granted Nov 2024 | Dec 2024 | East Hertfordshire | 6.1 |
| Herts And Essex High School, Warwick Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2024 | Oct 2024 | granted Nov 2024 | Dec 2024 | East Hertfordshire | 6.4 |
| Hockerill Anglo European College, Dunmow Roadrooftop solar | rooftop solar | 0.3 | application submitted may be out of dateupdated Jan 2024 | Jan 2024 | — | Jan 2024 | East Hertfordshire | 6.8 |
| Hockerill Anglo European College, Dunmow Roadrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Jul 2024 | Jan 2024 | granted Jun 2024 | Jul 2024 | East Hertfordshire | 6.8 |
| Rolls Farm Barns, Hastingwood Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2023 | Oct 2022 | granted Jan 2023 | Mar 2023 | Epping Forest | 7.2 |
| Wrights Flour Mills, Roydon Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Harlow | 7.2 |
| Icon Harlow, Unit Brooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | Harlow | 7.4 |
| Icon Harlow, Unit Crooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | Harlow | 7.4 |
| Icon Harlow, Gsk Third Avenuerooftop solar | rooftop solar | 0.6 | refusedupdated Sep 2023 | Jul 2023 | refused Sep 2023 | Sep 2023 | Harlow | 7.6 |
| Icon Industrial Estaterooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Harlow | 7.7 |
| Gsk Icon Harlowrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Harlow | 7.8 |
| Icon Harlow, Third Avenuerooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | Harlow | 7.9 |
| Great Notley Field, Bromley Lanesolar farm | solar farm | 0.3 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | East Hertfordshire | 8.3 |
| Wickham Hall Estatebattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Nov 2021 | granted Dec 2023 | Feb 2026 | East Hertfordshire | 9.0 |
| Parsonage Farm Solar PV Farm & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Mar 2026 | Jul 2025 | granted Jan 2026 | Mar 2026 | Uttlesford | 9.3 |
Distance from the average position of the CM21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 1 | 5 | 0 | 0 | 135 |
| Rooftop solar | 17 | 1 | 14 | 0 | 2 | 8.2 |
| Battery storage | 5 | 0 | 4 | 0 | 0 | 10.2 |
MW in pipeline: pending, approved and under-construction capacity.
How East Hertfordshire decides solar, wind and battery applications
| Applications | East Hertfordshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 20 | 10,236 |
| Refused | 7 (35%) | 19% |
| Solar refused | 4 of 13 | 12% |
| Onshore wind refused | 2 of 2 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 22.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in East Hertfordshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CM21, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.