Wickham Hall Estate Solar Photovoltaic Farm (35 MW)

Wickham Hall Estate Solar Photovoltaic Farm is a 35 MW solar farm project in East Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 December 2023, not yet built; the record was last updated on 23 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWsolar farm
approved, not builtstatus in REPD
23 February 2026record last updated
East Hertfordshirecouncil area

Planning timeline

DateStage
30 November 2021Application submitted
19 December 2023Planning permission granted
19 December 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
23 February 2026
Operator or applicant
Endurance Energy Wickham Hall Limited
Planning authority
East Hertfordshire
Planning application reference
3/21/2601/FUL
Site area
114.0 ha
Address (REPD)
Land At Wickham Hall Estate Bishops Stortford
Council area (by location)
East Hertfordshire
Time to decision
107 weeks
Contracts for Difference
AR7a
REPD reference
8485

Recorded together with Wickham Hall Estate (battery storage, approved, not built).

Who decides

ApplicationsEast HertfordshireUK
Decided applications (solar, wind, battery)2010,236
Refused7 (35%)19%
Solar refused4 of 1312%
Onshore wind refused2 of 245%
Battery storage refused1 of 516%
Median time from submission to decision22.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wickham Hall Estatebattery storage10approved, not built0.7
Wickham Hall Estate Solar Photovoltaic Farmsolar farm20approved, not built0.7
Hadham Roadbattery storage10permission expired1.6
Maggots End Road, Berden Solar Farm & Battery Storagesolar farm49.9refused4.5
Greens Farmbattery storage50approved, not built4.6
Pelhambattery storage49operational5.1
Berden Hall Solar Farmsolar farm56approved, not built5.1
Ginns Road, Stocking Pelhambattery storage400approved, not built5.3
Stocking Pelhambattery storage50refused5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8916, 0.1187).