Stocking Pelham (50 MW battery storage)

Stocking Pelham is a 50 MW battery storage project in East Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 30 June 2025; the record was last updated on 15 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
refusedstatus in REPD
15 June 2026record last updated
East Hertfordshirecouncil area

Planning timeline

DateStage
27 April 2022Application submitted
30 June 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
refused
Record last updated
15 June 2026
Operator or applicant
Renewable Connections
Planning authority
East Hertfordshire
Planning application reference
3/22/0806/FUL
Address (REPD)
Crabbs Lane And Pelham Substation Stocking Pelham
Council area (by location)
East Hertfordshire
Time to decision
166 weeks
Name in REPD
Stocking Pelham - Battery Storage System
REPD reference
11212

Who decides

ApplicationsEast HertfordshireUK
Decided applications (solar, wind, battery)2010,236
Refused7 (35%)19%
Solar refused4 of 1312%
Onshore wind refused2 of 245%
Battery storage refused1 of 516%
Median time from submission to decision22.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pelhambattery storage49operational0.3
Dellows, Ginns Roadbattery storage90application submitted0.3
Greens Farmbattery storage50approved, not built0.8
Ginns Road, Stocking Pelhambattery storage400approved, not built0.8
Berden Hall Solar Farmsolar farm56approved, not built1.0
Maggots End Road, Berden Solar Farm & Battery Storagesolar farm49.9refused2.5
Wickham Hall Estate Solar Photovoltaic Farmsolar farm35approved, not built5.3
Wickham Hall Estatebattery storage10approved, not built5.8
Wickham Hall Estate Solar Photovoltaic Farmsolar farm20approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9396, 0.1177).