Greens Farm (50 MW battery storage)

Greens Farm is a 50 MW battery storage project in East Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 July 2025, not yet built; the record was last updated on 28 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
28 July 2025record last updated
East Hertfordshirecouncil area

Planning timeline

DateStage
5 May 2021Application submitted
18 July 2025Planning permission granted
18 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
28 July 2025
Operator or applicant
Cambridge Power
Planning authority
East Hertfordshire
Planning application reference
3/21/0969/FUL
Address (REPD)
Greens Farm, East End, Stocking Pelham, Buntingford
Council area (by location)
East Hertfordshire
Time to decision
219 weeks
Name in REPD
Greens Farm - Battery energy storage
REPD reference
9012

Who decides

ApplicationsEast HertfordshireUK
Decided applications (solar, wind, battery)2010,236
Refused7 (35%)19%
Solar refused4 of 1312%
Onshore wind refused2 of 245%
Battery storage refused1 of 516%
Median time from submission to decision22.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pelhambattery storage49operational0.6
Stocking Pelhambattery storage50refused0.8
Ginns Road, Stocking Pelhambattery storage400approved, not built0.9
Dellows, Ginns Roadbattery storage90application submitted1.0
Berden Hall Solar Farmsolar farm56approved, not built1.2
Maggots End Road, Berden Solar Farm & Battery Storagesolar farm49.9refused2.4
Wickham Hall Estate Solar Photovoltaic Farmsolar farm35approved, not built4.6
Wickham Hall Estate Solar Photovoltaic Farmsolar farm20approved, not built5.1
Wickham Hall Estatebattery storage10approved, not built5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9329, 0.1152).