Solar, wind and battery projects near Saffron Walden (CB11)
17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CB11 (Uttlesford): 1 is waiting for a planning decision, 7 approved but not yet running, 2 operational. The largest live scheme is Ginns Road, Stocking Pelham (400 MW battery storage, approved on 29 April 2025, not yet built), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CB11
Projects of 1 MW and more (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Long Meadow Solar Farmsolar farm | solar farm | 19 | operationalupdated Jul 2025 | Jan 2021 | granted Apr 2023 | Jul 2025 | Uttlesford | 5.1 |
| Butlers Farmsolar farm | solar farm | 7.7 | refused on appealupdated Apr 2016 | Sep 2014 | refused Mar 2015 | Apr 2016 | Uttlesford | 6.4 |
| Chesterford Park - Green Energy Hubsolar farm | solar farm | 2.8 | approved, not built may be out of dateupdated Sep 2021 | Sep 2021 | granted Dec 2022 | Sep 2021 | Uttlesford | 7.0 |
| Thaxted Solar farmsolar farm | solar farm | 40 | approved, not builtupdated Jan 2024 | Jun 2021 | granted Sep 2022 | Jan 2024 | Uttlesford | 8.6 |
| Berden Hall Solar Farmsolar farm | solar farm | 56 | approved, not builtupdated Jun 2026 | Aug 2022 | granted Jul 2024 | Jun 2026 | Uttlesford | 8.9 |
| Maggots End Road, Berden Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | refusedupdated Mar 2026 | May 2025 | refused Jan 2026 | Mar 2026 | Uttlesford | 9.0 |
| Stocking Pelhambattery storage | battery storage | 50 | refusedupdated Jun 2026 | Apr 2022 | refused Jun 2025 | Jun 2026 | East Hertfordshire | 9.2 |
| Dellows, Ginns Roadbattery storage | battery storage | 90 | application submittedupdated Sep 2025 | Jun 2025 | — | Sep 2025 | East Hertfordshire | 9.3 |
| Abbey Farmsolar farm | solar farm | 5 | application withdrawnupdated May 2016 | Oct 2015 | — | May 2016 | South Cambridgeshire | 9.3 |
| Pelhambattery storage | battery storage | 49 | operationalupdated Jan 2019 | Aug 2016 | — | Jan 2019 | East Hertfordshire | 9.3 |
| Rectory Farmsolar farm | solar farm | 5 | application withdrawnupdated May 2016 | Oct 2015 | — | May 2016 | South Cambridgeshire | 9.4 |
| Greens Farmbattery storage | battery storage | 50 | approved, not builtupdated Jul 2025 | May 2021 | granted Jul 2025 | Jul 2025 | East Hertfordshire | 9.9 |
| Ginns Road, Stocking Pelhambattery storage | battery storage | 400 | approved, not builtupdated Jul 2025 | Nov 2024 | granted Apr 2025 | Jul 2025 | East Hertfordshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Chesterford Park - Green Energy Hubbattery storage | battery storage | — | approved, not built may be out of dateupdated Sep 2021 | Sep 2021 | granted Dec 2022 | Sep 2021 | Uttlesford | 6.7 |
| Thaxted Solar farmbattery storage | battery storage | — | approved, not builtupdated Jan 2024 | Jun 2021 | granted Sep 2022 | Jan 2024 | Uttlesford | 8.6 |
| Major Barclay Farms, Beeches Manorrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Nov 2024 | Sep 2024 | — | Nov 2024 | East Hertfordshire | 9.0 |
| Maggots End Road, Berden Solar Farm & Battery Storagebattery storage | battery storage | — | refusedupdated Mar 2026 | May 2025 | refused Jan 2026 | Mar 2026 | Uttlesford | 9.0 |
Distance from the average position of the CB11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 0 | 3 | 1 | 2 | 98.8 |
| Rooftop solar | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 8 | 1 | 4 | 1 | 2 | 540 |
MW in pipeline: pending, approved and under-construction capacity.
How Uttlesford decides solar, wind and battery applications
| Applications | Uttlesford | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 35 | 10,236 |
| Refused | 11 (31%) | 19% |
| Solar refused | 7 of 24 | 12% |
| Battery storage refused | 4 of 11 | 16% |
| Median time from submission to decision | 20.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CB11, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.