Long Meadow Solar Farm (19 MW)

Long Meadow Solar Farm is a 19 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2025; the record was last updated on 28 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWsolar farm
operationalstatus in REPD
28 July 2025record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
21 January 2021Application submitted
21 April 2023Planning permission granted
1 June 2025Operational

Project details

Technology
solar farm
Capacity
19 MW
Status (REPD)
operational
Record last updated
28 July 2025
Operator or applicant
Low Carbon Solar Park 4 Limited
Planning authority
Uttlesford
Planning application reference
UTT/21/0688/FUL
Site area
54.9 ha
Address (REPD)
Land At Cole End Farm Lane Wimbish Essex
Council area (by location)
Uttlesford
Time to decision
117 weeks
Contracts for Difference
AR5
REPD reference
8824

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Butlers Farmsolar farm7.7refused on appeal4.0
Thaxted Solar farmsolar farm40approved, not built5.8
Spriggs Farmsolar farm12operational7.3
Terriers Farmsolar farm44operational7.4
Hyde Farmsolar farm10.8operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0076, 0.2855).