Hyde Farm (10.8 MW solar farm)

Hyde Farm is a 10.8 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 November 2014; the record was last updated on 14 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.8 MWsolar farm
operationalstatus in REPD
14 November 2014record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
27 August 2013Application submitted
22 November 2013Planning permission granted
13 November 2014Operational

Project details

Technology
solar farm
Capacity
10.8 MW
Status (REPD)
operational
Record last updated
14 November 2014
Operator or applicant
Lightsource Renewable Energy / Push Energy
Planning authority
Uttlesford
Planning application reference
UTT/13/2207/FUL
Site area
18.0 ha
Address (REPD)
Hydes Solar Farm Little Bardfield Braintree Essex
Council area (by location)
Uttlesford
Time to decision
12 weeks
REPD reference
1322

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Spriggs Farmsolar farm12operational1.8
Terriers Farmsolar farm44operational1.9
Thaxted Solar farmsolar farm40approved, not built4.8
Tooleys Farmsolar farm5.3operational8.1
Long Meadow Solar Farmsolar farm19operational9.1
Merks Hill Farm, Braintree Road Solar Farmsolar farm12application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9581, 0.3907).