Energy Projects Near You

Terriers Farm (44 MW solar farm)

Terriers Farm is a 44 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2022; the record was last updated on 16 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

44 MWsolar farm
operationalstatus in REPD
16 January 2026record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
31 July 2019Application submitted
9 January 2020Planning permission granted
26 April 2021Construction started
1 February 2022Operational

Project details

Technology
solar farm
Capacity
44 MW
Status (REPD)
operational
Record last updated
16 January 2026
Operator or applicant
Low Carbon
Planning authority
Uttlesford
Planning application reference
UTT/19/1864/FUL
Site area
52.3 ha
Address (REPD)
Land At Terriers Farm, Boyton End, Thaxted, Dunmow
Council area (by location)
Uttlesford
Time to decision
23 weeks
REPD reference
6700

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Spriggs Farmsolar farm12operational0.5
Hyde Farmsolar farm10.8operational1.9
Thaxted Solar farmsolar farm40approved, not built3.0
Long Meadow Solar Farmsolar farm19operational7.4
Tooleys Farmsolar farm5.3operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9631, 0.3649).