Tooleys Farm (5.3 MW solar farm)

Tooleys Farm is a 5.3 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 8 October 2015; the record was last updated on 5 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.3 MWsolar farm
operationalstatus in REPD
5 January 2016record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
16 September 2014Application submitted
16 December 2014Planning permission granted
20 July 2015Construction started
8 October 2015Operational

Project details

Technology
solar farm
Capacity
5.3 MW
Status (REPD)
operational
Record last updated
5 January 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Uttlesford
Planning application reference
UTT/14/2739/FUL
Site area
10.9 ha
Address (REPD)
Site At Tooleys Farm, Brookend Road, Stebbing, Dunmow, Essex
Council area (by location)
Uttlesford
Time to decision
13 weeks
REPD reference
4859

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Merks Hill Farm, Braintree Road Solar Farmsolar farm12application submitted1.8
Solar Farm at W/O A120 Chelmsford Roadsolar farm9.9under construction2.7
Drapers Farm Solar Parksolar farm6operational7.8
Hyde Farmsolar farm10.8operational8.1
Felsted School Road Solar Photovoltaic Farm & Battery storagesolar farm49.9approved, not built8.5
Stanstead Solar Projectsolar farm14.3under construction8.8
Terriers Farmsolar farm44operational8.9
Spriggs Farmsolar farm12operational9.3
Slamseys Energy Storagebattery storage10under construction9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.885, 0.3944).