Energy Projects Near You

Drapers Farm Solar Park (6 MW)

Drapers Farm Solar Park is a 6 MW solar farm project in Uttlesford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2014; the record was last updated on 20 May 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
operationalstatus in REPD
20 May 2014record last updated
Uttlesfordcouncil area

Planning timeline

DateStage
15 March 2013Application submitted
7 June 2013Planning permission granted
26 September 2013Construction started
30 March 2014Operational

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
20 May 2014
Operator or applicant
Lightsource Renewable Energy
Planning authority
Uttlesford
Planning application reference
UTT/13/0561/FUL
Site area
15.6 ha
Address (REPD)
E/O Milch Hill Lane, Great Leighs, Chelmsford, Essex, CM3 1QF
Council area (by location)
Uttlesford
Time to decision
12 weeks
REPD reference
1658

Who decides

ApplicationsUttlesfordUK
Decided applications (solar, wind, battery)3510,236
Refused11 (31%)19%
Solar refused7 of 2412%
Battery storage refused4 of 1116%
Median time from submission to decision20.0 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Essex, Uttlesford.

Other large projects within 10 km

ProjectTypeMWStatuskm
Felsted School Road Solar Photovoltaic Farm & Battery storagesolar farm49.9approved, not built0.8
Slamseys Energy Storagebattery storage10under construction1.8
Braintree Road, Cressingbattery storage57under construction5.6
Cressing Solar Farm (Phase 1)solar farm5operational7.3
Cressing Solar Farm (Phase 2)solar farm18abandoned7.3
Cressing East Solar Farmsolar farm24.9approved, not built7.4
Tooleys Farmsolar farm5.3operational7.8
Cressing Farm, Witham Road Solar Farmsolar farm13.8approved, not built7.9
Solar Farm at W/O A120 Chelmsford Roadsolar farm9.9under construction8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8562, 0.4983).